Answer Posted / manish sharma

Lead Time: This is the amount of time takes to produce the
first assembly, from start to finish on the production line.

Manufacturing Lead Time: The total time required to make an
item if you had all raw materials in stock but had to make
all subassemblies level by level. Oracle Bills of Material
automatically calculates this value, or you can manually
assign a value.
BOM sets an item's cumulative manufacturing leadtime using
the following:

1) Manufacturing leadtime for the item.
+
2) Maximum [(cumulative mfg leadtime - offset days)
for any component in bill]

Total Leadtime: The fixed lead time plus the variable lead
time multiplied by the order quantity. The planning process
uses the total lead time for an item in its scheduling
logic to calculate order start dates from order due dates.

Total Lead Time is the Fixed Leadtime + (Variable Leadtime
* Order Quantity).

Cumulative Total Lead Time: The total time required to make
an item if no inventory existed and you had to order all
the raw materials and make all subassemblies level by
level. Bills of Material automatically calculate this
value, or you can manually assign a value. BOM sets an
item's cumulative total leadtime using the following:

1) Total leadtime for the item.
+
2) Maximum [(cumulative total leadtime - offset
days) for any component in bill]

Is This Answer Correct ?    2 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

List out the tables in basic oracle apllication modules?

3172