Answer Posted / suresh ch
1 cum Cement = 1440 Kgs so 1440/50 = 28.8 bags
Is This Answer Correct ? | 11 Yes | 0 No |
Post New Answer View All Answers
I need Bhel engineertrainy test papers in civil engineering please send to email id - hisandy66@gmail.com
Suppose a new brick wall is being constructed,and the courses and not aligned horizontally,what negetives can it cause?
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..
silt%= silt volume/ silt+sand volume is this right?
A rock anchor 3 1/2” in diameter is placed in rock. The which has an allowable shear strength of 1200 psi. Determine the required anchorage length to safely carry a 80 ton load using a 2.0:1 F.S
Explain the benefits of using standard terminology in the measurement process?(Tendering and estimation)
How to design 12*12*14 room having rrc slab ,coloum, beam,foundation?
All aptitude question of Bechtel
Is it possible to make a feature using an overdefined sketch?
how many material required for brickbat water proofing of toilets.
how do you calculate the length of "L" of main & distribution bar for reinforcing of raft footing
How much wastages taken in 1. cement 2. steel 3. fine aggregate 4. coarse aggregates (10mm, 20 mm)
How much quantity water should be placed in one cubic meter area?
Define What are the materials used in building a gravity dam?
What is the value of live load that should be incorporated in design of locker room and cash vault room while designing a building for commercial bank?