Slump test is carried out for measure workiability of
concrete. it telles about water cement ratio present in
concrete. generraly we kept this ratio is between 25 to
100mm.
slump is less than 25mm water present is very low if
greater than 80mm water present is very high.

Is This Answer Correct ?    35 Yes 5 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What Reinforcements Are Used In The Process Of Prestressing?

845


How to do base isolation using ETABS software?

2491


design the irrigation canal(b,B,h )head is 3tms of water is supplied to the 200hectars of area and the base period crop is 150days dance to water travels as 35km.the canal section is trapezoidal and also calculate the slop the canal

1803


What in your opinion makes you the most suitably qualified candidate for this post of civil engineering technician?

701


what is the anchorage length of reinforcement.

1308






What is Density of cement, sand & aggregate ?

1065


density of crush sand & crush stone or grit powder

6311


How much does it cost for a R.C.C cover slab of size (450mmX 600mmx 100mm) double rf net given in feets using hand mix concrete?

1450


plumbing CPVC fitting FTE Brass full form

2136


What is the difference between a wood shake and wood shingles?

705


Can a wave happen in the middle of the ocean like in the movie poseidon 2006?

697


What is the use of array command?

699


What are the RISKS during the project construction?

1741


How much quantity water should be placed in one cubic meter area?

901


In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

1681