why VCB are not used in 132KV system(above 33KV system)
Answer Posted / nihar ranjan mandal
Amount of vacuum required to quench the arc at 132 KV level
will be very high. It is difficult to maintain that amount
of vacuum in practical purpose. Now a days we use GIS( gas
insulated substation for 132KV level. Where arc is quenched
in hydrogen chamber.
| Is This Answer Correct ? | 16 Yes | 1 No |
Post New Answer View All Answers
In Power Line Communication (PLC) the wave trap is used to block communication signals from entering neighboring lines. My question is this: Why do they allow for different filtering arrangements on these wave traps? Isn't it always going to be a low pass filter since we want the power frequency to go through, and the comm signal blocked?
we have amp, voltage, kw, length detail then how to calculte copper & alluminium size of conductor of 3-phase induction motor
what is load vs Torque curve & why it is used?
Discribe type of fault in DOL and stardelta startor.
we have consol make 3 phase servo stabilizer for cnc m/c. while installing the earth neutral voltage is 1.7 volts at stbilizer off condition and when stabilizer get on en voltage reaches 4.8 volts (new earthing is done and neutral is helthy condition all phase to neutral volts 440,442,441 v)why this happen.solution for cause.
How will polarity test of Dy5 Transformer ?
can u give me a brief idea about power line carrier communication ??
what is the meaning of the symbol << >> put in transformer drawing
What is the use of lag compensator?
how to calculate the conductor size for certain KV transmission line and distribution line?
in what type of applications v can use q meter?
at work we have a 3 phase motor but on testing one phase isnt getting a reading. it runs 24 hours a day all week. stops and starts well no noise or heating. the phase isnt down to earth.is it just a bad meter reading or not? phases one and three came up with a resistance reading of 0.4 but phase 2 couldnt get anything shows up as open circuit.
If I have 3 essential main switch board and 3 incoming electricity ,but only 1 genset running is that possible.
how solar power plant energy meter multiplication factor
how can service sitting be setted for MCCB?Example for sittings IR (CURRENT RATING),IS(CURRENT STARTING)IO (current operating)?