Answer Posted / nagori salim
Vol of 1 bag of cement = 50/1440
= 0.0347 cumec
For 1 cumec = 1/0.0347
= 28.818
= 29 bags
| Is This Answer Correct ? | 17 Yes | 2 No |
Post New Answer View All Answers
what are the duties of Site Engineer in work site?
Can compresive strength test for concrete at 1 day age possible to carry out? If yes, which IS code describes the procedure for such testing?
What is alternate bid?
what is the types of door's wood?
weight of 1 cft 10mm, 20mm, 40mm aggregate weight of 1cft course sand
How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)
For making a new road in a village having a school & hospital , tell the steps of construction systemically ?
What is the name of this multiplication factors ?
Sir how to find cutting length for footing steel bars in the shape of "u"
sir i want to know that in L & T construction can we do our 6 months training proggramme cum placement???????
What is the difference between shear and tensile strength?
What are the techniques to measure road difference?
How to come 1.54 from dry to wet concrete?
how to calculate testing date
How does a traffic light signal work ?