plz give me the rate of RCC(1cuM), PCC(1 cuM), Brick Work
(1sqM)?

Answer Posted / ehaque9499

If PCC is M10 (1:3:6) cost will be about 3000 Rupees per
Cum and RCC of M20 or 25 cost around 4500. Brick cost will
be depend upon brick rate if brick Rs 3 per no. then cost
3000 Rupees per Cum.

Is This Answer Correct ?    22 Yes 14 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is the weight of 10mm,20mm,40mm aggregate

2004


If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?

1379


what is the composition of good brick ?

1461


what is hydrostatic paradox?

1711


What is the difference between EPC,DBOOT and BOOT.

23347






What are the alternate material for steel, Sand and aggregate

1828


how to estimate material requirement for an area of house in square feet?

1736


Describe the role of independent Quantity surveyor?

2446


does a b.tech civil engineer fresher supposed to know how to design rcc structure?

3009


how to find quantity of concrete in PCC M15

1680


01. a. Diagram of a slump cone…………… 1 b. Size of Slump Cone…………… 1 c. Volume of a slump cone by av. Dia method…………… 1 d. Volume of a slump cone by av. area method…………… 1 e. Volume of a slump cone by frustrum method …………… 1 f. Angles of slump cone …………… 1 g. Slump measured by slump cone due to…………… 1 h. Slump does not measured by cylinder / cube due to …………… 1 i) ii) i. Slump cone is to be filled in……………………..Layers.

5058


Thumb rule for steel qty for 1m2 in kg/m2 column slab footing beam

5123


What is the FE 250 structural steel of 8mm tk plate testing sample intervals with IS code or international code?

1852


What is the quantity of cement in mix m20 concrete?

693


Can inverted beams used in pipes during construction?

870