what is the height between the reflux pump and condenser ?
Answer Posted / kashif
I Have installed Reflux Pumps at 0.0mtrs Ground Level While
Reflux Pot is at 5.0 mtrs Level and condensors are at 13.5
mtrs Level ,its Working Satisfactory.
While in another case reflux Pot is at 5.0mtrs and
condensor is at 10.0mtrs and Reflux Pumps are at Ground
0.0mtrs Level. This column is used for Methanol
Distillation.
Is This Answer Correct ? | 5 Yes | 4 No |
Post New Answer View All Answers
Under what circumstances are vortex flowmeters the most accurate?
What are the methods involved to test helium leak testing in a vacuum system?
What is a good way to get started in doing a plant-wide steam consumption analysis?
What are some common problems associated with bellow expansion joints?
Define condensate lift?
Does home used kerosene which is available in blue color can change its color after keeping number of years (say 8-10 years)? If yes, then in which color will it turned to? Will it change to yellow color or transparent color? Please reply with suitable technical suggestion/approach. Its an important question which was asked. I need a very strong technical reply. Please help me.
Explain the some guidelines for sizing a psv for a fire scenario on a vessel in a refinery service?
What are angle of repose applications in the chemical industry?
In a crusher where is the energy provided to it is used up for?
Where barrel pump use?
What is the ignition temp. of Alluminium,Coper&Iron.
design calculations for reactor
What are some common methods for helium leak testing a vacuum system?
Explain what particle sizes are electrostatic precipitators used to remove?
Explain the functioning of a three-way catalytic converter.