what should be distance between two electrical earthing pit
as per i.e.e
Answer Posted / vishwas bhat
distance between two pits should not 3m bcoz there is a
tecnical reason behind it, and the reason is that when
there is some heavy earth fault and if one of the pits is
acting as a returning path for earth fault current then it
might go dry due to heat dissipation by the passing
current, and simultaneously one more heavy fault happens
then these pits will offer high resistance because they
have lost moisture and which is not desirable, hence the
distance between two 3m pits should be minimum 6mts.
| Is This Answer Correct ? | 67 Yes | 12 No |
Post New Answer View All Answers
What does the a,b,c of 95a,95b,95c relays denotes?
HOW TO SET THE EARTH FAULT SETTINGS IN ACB????????????
HOW TO WORK A VFD?SAY SIMPLE METHOD
Why two phase welding machine is used instead of three phase welding machine.
Dear sir, my knowledge about cable size determination is limited. Though I read examples I could not calculate the Cable size required for electric driven pump 40 KW, 380 Volt, 50 HZ, 50 meter from transformer and it is three phase star delta starting. Please help as there is no one in my surroundings to help.
Is it required to do earthing in 2nd shop if earthed armoured cable is laid from 1st shop ?
The windings of a transformer are divided into several coils, because?
Define resonant peak?
In which of the following case, the rotating magnetic field is reversed? A regenerative breaking B plugging C dynamic breaking D forward motoring
What fomula is used to calculate: 1. rated frequency withstand voltage, and 2. rated lightning impulse withstand voltage.
What do you understand by external characteristics of a d.c. Generator?
If we connect a motor and generator together (I mean that the generator gives the motor electricity and the motor gives the generator movement) regardless the losses. Will the generator still generate and the motor still move?
how can get electrical "c" licence.i am complited in DEEE.PASSING YEAR OF 1993.WORKING IN PVT COCERN LT LINE.PLEASE ADVISE ME .CELL NO 9994786021
pls someone send me sample question papers along with the key.thanks in advance
How Calculet The UPS AH In Load