in trains i have seen the terminal which is connected at
the top of the train is positive .where is negative ?
track? i dont think so

Answer Posted / manesh.k

Actually,it is good to refer it as Phase & neutral
itself,since,as per Indian railways we use 25kV,1 phase ac
system.The terminal at top ie called panthograph takes power
in to loco and track acts as neutral

Is This Answer Correct ?    7 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How many types of protection relays are there based on the characteristic?

605


I am inpecting a 10kVA UPS what tests should i do and should i observe?

1799


What is PEC??Applications........

1510


We normally make oil soak pits under Transformers. Oil from soak pit goes to collection pit. We provide granules/pebbles under transformers. My question is weather granules/ pebbles to be filled in soak pit or not? if yes upto what level?

9886


Which motor is 3.3 or 11kV more reliable, in terms of efficeancy,maintenance, reliability.

1614






Explain the term parallel path in dc machin ?

1765


what is mean by drives?

1498


will 1050kva DG set withstand for back charge of 16MVA transformer

1461


why is the conservator tank painted white on the transformer

2573


What is the application of Dyn1 and Dyn11 vector group of transformer?

2434


Do Phase angle measurement have any application in freq/harmonics measurement? If so how?

1463


Define liftable weight of a transformer? Does the total weight of transformer include oil weight?

2068


Electrical Engineering

1508


how to calculate the cable current ratingand and how much of distance the rating will be ok will the distance is incresed what the action we take

1620


WHAT IS AIR GAP VALUE IN MM FOR A 11KV BUSHING OF 11KV/440V DISTRIBUTION TRANSFORMER. AND AIR GAP VALUE OF 25 KV BUSHING OF AT TRANSFORMER OF 25 KV TRACTION. WHAT IS THE CALCULATION FOR THE AIR GAP PERMITTED FOR BUSHINGS AT DIFFERENT VOLTAGES.

3049