In case of a beam ,main steel is provided along the longer
span because, bending moment is directly proportional to
length but why in case of one way slab main steel is
provided along shorter span while as bending takes place
along longer span?comment

Answer Posted / shanmuga sundari

in case of beam b.m takes place along the lenth so main bar
is provided in tat direction to resist b.m.but in case of
one way slab the bm along longer direction is too low as
compared to shorter direction so resisting this bm
distribution bar is enough.so main bar is provided in
shorter direction and also l/b ratio is greater than 2.

Is This Answer Correct ?    4 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How can we calculate 8- storied Madrasha Building pile capacity by taking SPT value at site?

1575


What is difference between combin footing & rapt footing

1132


List out some of the checking’s, done at the completion of construction?

709


What are the advantages of cad?

643


Formula of mid span bar

1467






Sometimes the side of concrete bridges is observed to turn black in color. What is the reason for this phenomenon?

698


What is the tensile strength of wood?

664


States some of the tool bars used in cad?

678


what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?

1671


My daily concrete volume of M25 concrete is 1st day= 25 Cum 2nd Day = 45 Cum 3rd Day = 55 Cum 4th Day = 22 Cum 5th Day =72 Cum 7th Day = 49 Cum. What will be acceptance criteria of concrete considering as per is 456 cl.15 and table 11 (cl 16.1 and 16.3).

2619


How much cement,sand,bricks and water needed for 1square metre brick work?

1344


What is the difference between undo & redo?

731


Rate analysis of Vitrified tile in cement mortor 1:3

3939


Find out Cutting Length of Steel for Right angle Triangle? Where Opposite Side 4m, Adjacent side 6m. (Assume cover 40mm)

1466


i have to give lap joint fo 1Mtr steel of dia12mm,whenever i did mistake i cut less 5cm plz tell me how much i will give lap joint so that length comes 1Mtr

1553