How do you determine realistic schedules for the project?

Answer Posted / hyejung kwon

According to Verzuh, a realistic schedule:
-Includes a detailed knowledge of the work to be done
-Has task sequences in the correct order
-Accounts for external constraints beyond the control of
the team
-Can be accomplished on time, given the availability of
skilled people and enough equipment

There are steps to follow to create realistic project plan.
Step one: Create a work breakdown structure
Step two: Identify task relationships (Network
Diagrams/PERT Charts)
Step three: Estimate work packages
Step four: Calculate an initial schedule
Calculating the schedule is a three-step process; forward
pass, backward pass, and calculate float. Forward pass
helps you determine the early start (ES) and early finish
(EF) for each task. Backward pass determines the late start
and late finish dates. Calculate float means flexibility in
the schedule and calculated buy subtracting early start
from late start. Critical path has no float, so it should
begin and finish on time.
Step five: Assign and level resources
Resources mean the people, equipment, and the materials.
And the leveling follows a four-step process:
1. Forecast the resource requirements throughout the
project for the initial schedule.
2. Identify the resource peaks.
3. At each peak, delay noncritical tasks within their float.
4. To eliminate the remaining peaks, reevaluate the work
package estimates.
This detail and realistic schedule may not solve all the
problems but wil provide a tool set for solving many of
them.

Is This Answer Correct ?    79 Yes 11 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Do you personally involved with Major incident process ? If yes, how do you manage it in your present organization ? explain with real scenario !

1290


i was looking for a general example for time management and how everything is linked together so i can have a complete picture. when i say link i mean with OM and PA and work schedule,planned working time, other relevant infotypes, personnel area and subarea and their groupings, etc...

2050


i am going for the IT Officer written test,can any body mail me the question bank to Pragyanmund@rediffmail.com

1931


DataStage 7.5 & DataStage 8.5 :Which Oracle Database version is supported as target datasource?

2926


Why are you interested in this position? Our company?

3752






why u choose mba after bca?

25553


state the role of cost accounting in large scale industry

1672


what is erp manufacturing perspective??

3897


cost accounting is a tool for dicission making expline

1648


what do u mean by altkey?

1949


How retrive the deleted file frm UAT by doing migration in SAP BO 4.0

1815


If you are a team lead in any IT company, and two employees are under your supervision. If one employee is good and other cannot behave professionally and personally, then how will you handle this situation?

2095


sir iam going for an interview on feb 2nd week and i would like too ask questions that they will pose too me 1:i hav choosen conchordia wisconsin why these university what should b my answer 2:i had selected mis in mba from conchordioa university why these course if they question wat should b my answer 3:and last question is wat is guarantee u will come bck my dad works as a production manager in saudi arabia soo wat should b my anser too them because i am going for mba wat should b my answer for return gurantee pls reply too me it will b gr8 off u yours sicerly

1630


i have completed my bca from annamalai university in distance mode. Now am working as a Front Office Executive in a Software co. I am interested in HR field. and i want to do MBA HR from symbiosis university through Distance mode..Am i thinking right for myself??? please suggest me.!

2031


How to Cancel SAP PO against Fix transport?

1775