In osp cycyle
i have one finished goods -FG1
Raw material - RM1
Osp Item - OSP1
Resource -Ospres01
Charge Type -PO Move
I assign dept, then i created routing and bom.
then i realsed job
the PO requestion Generated
But when i replace on another OSP ITEM - OSP2 for OSP1
having same attributes
i am not getting Po requestion
CAn any one help me?
Thanks in advance,
Raghunandana
raghu.nandana@rediffmail.com
Answer Posted / sahil
1) Where are u changing the OSP2 item in place of OSP1.
2) See that the OSP2 is linked to the approved supplier list
and all the sourcing rule and everything is properly setup.
3) Po requisition will be only created when u properly
define the setups required for creating the automatic po
requisition