11kv/0.433kv, 2 mva , transformer , for protection and
metering how many CT/PT are required?
Answer Posted / k n naidu
hi,
one three phase set of PTs for both protection & metering
and one three phase set of CTs with two secondary cores one
for metering and protection are required.
Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
how i can calculate the size for fire cable
What does the term power factor shows?
What are the significant parts of dc generator?
Hoe do calculate the Cable size for Amps rating ?
(1)Can earth and be conected together (2) what is the diferent between earth & neutral
best manufacturer for busbar for outdoor switchyard having double bus bar scheme, can any one share technical specification of busbar. 132kv voltage ?
how to setting Load amps tripping time and extra settings for load Transformer protection relay with RMU panel using C&S model relay..?
HOW WORK HEAT PLATE EXCHANGER
any body,pls tell me how to done relay coordination ? how to coordinate by TCC curve?how to read the tcc curve?
sir i want previous entrance exam papers for written test
How to derive detailed design of Suitable bus Bar for 100A for 6.6KV?
what is the difference between earthing and unearth
what is meaning of bus riser
What are dependent sources?
What is the difference between electrical earthing and electrical grounding?