Answer Posted / nanduri k. prasad
MPS :- Master Production scheduling is generally done for
when the product groups exists. By doing MPS we basically
disagreegate the group requirements into individual product
requirements. By doing MPS we can disagreegate the plan and
we can only creat planned order for finished products.
MRP :- Materials requirment planning is done to drill down
for individual product once the planned orders for finished
products are created by MPS. However, we can use only MRP
for any individual material anytime.
| Is This Answer Correct ? | 19 Yes | 9 No |
Post New Answer View All Answers
How can you create production order without routing and BoM?
Question related to Production order status or status profile?
Why and how you calculate WIP?
What happens to planned after it has been converted into production order ?
Which tool you are using
Explain the stock requirement list and their uses.
Explain what is the need of mrp list if the stock requirement list is already given?
We want the system to run a single level mrp automatically on receipt of sales order. How to configure triggering event based mrp?
What is the use of sap material view and list out other parameters where sap material view is applicable?
Can we have more than 6 standard values in standard value key?
What is alternative BOM, or diff between BOM group and Group BOM?
Difference between standard cost and variable cost.
Mention what is the use of t-code cs20 in bom?
What is serial number and where you will be configure
Differentiate ‘variant bom’ from ‘multiple bom’?