what r the activites we have to do before just golive ?
Answer Posted / mmreddy
Hi,
Before golive we have done the following activities.
1.Finalise the entire system configuration.
2.done all testing like integration testing,gui testing etc
3.Cutover activities mean uploading of all master datas
4.user training.
Regards,
Mallesh.
| Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
What does field status group assigned to a gl master record controls? : fi- general ledger
HOW ARE SAP FICO JOBS RIGHT NOW?
Explain production set-up in fi-aa? : fi- asset accounting
How do you configure the gl account for the house bank? : fi- general ledger accounting
How do you deal with tax when you post an invoice? : fi- accounts payable
What are all the major issues you faced during implementation ?
What are the different submodules in sap fi?
when i post a billing document for free goods how can i exclude for a line item (cost element type 1),not to create a profitability segment but only a cost center thanks in advance
Can one chart of accounts be assigned to several company codes?46
What is a financial statement version? : fi- general ledger master data
What is "dunning" in sap?
Where can you use the internal order?
What do you mean by component scrap?
What are the major components of the chart of accounts?
What are the necessities of a dialog program must complete?