Answer Posted / satya
Go through the following steps.
1. Say i am providing three components A, B & C to get
ASSEMBLY from sub contractor vendor.
2. Create a Material master for Scrap material say D.
3. In BOM, maintain the Material D in negative quantity,
Say A - 1 off, B - 2 off , C - 2 off, D - 1 kg.
4. Now follow the regular process of subcontrating.
5. When you want to inward the scrap material from the
subcontractor end, first receive the material D with the
movement type 545 ( This will make the material available
in material provided to vendor stock ).
6. Then do a GR with 542 movement type to get the scrap
material in to plant stock ( ie reversal of 541- Goods
issue movement type)
| Is This Answer Correct ? | 17 Yes | 8 No |
Post New Answer View All Answers
Do we include consignment stock (material provided by vendor) in physical inventory? Why?
Explain lot sizing
What is mrp (material requirement planning)?
what is access number in access sequence how do we define that ?
What is valuation grouping code related to obyc?
How is consignment material procured?
What are some of the initial configuration steps for purchase requisitions?
Explain release strategy
How is the inventory management integrated with mm?
How is the mm module integrated with other modules of sap?
How is material information structured in material master records?
In bom I mentioned item category as l but when I create po for sub-contracting defaultly it shows t?
Explain mrp type
Explain the terms planned delivery and gr processing time?
Mention what are the major purchasing tables? List the transaction codes for them?