What are the settings required for quota arrangement?
Answer Posted / satya
To set up a quota arrangement for the procurement of a
material, proceed as follows:
Master data -> Quota arrangement -> Maintain, enter the
material and plant number, press ENTER to display the
overview screen for the quota arrangement periods, Enter a
validity period for quota arrangement, Enter date until
which the quota arrangement is valid. The start date is
calculated by the system. Press ENTER .
Select the quota arrangement and choose Goto -> Item
overview to display the item overview screen of the quota
arrangement. Enter a quota arrangement item for each
source of supply you want to include in the quota
arrangement.
You must enter the following data.
- Procurement type
- Special procurement type, Enter k in the S column, for
example, if a consignment arrangement for the material
exists with the vendor.
- Vendor number
- Procurement plant (supplying plant):
- Quota column, enter the quota assigned to each item.
Press ENTER .
The percentage distribution of the quotas is calculated and
displayed automatically by the system.
Save the quota arrangement. The system assigns a number to
the quota arrangement item automatically
| Is This Answer Correct ? | 12 Yes | 5 No |
Post New Answer View All Answers
when we doing migo storage location option not display
What is cbp?
How can we have 2 GL accounts using same valuation class in material master ? split valuation process example we are procuring materials from two different destinations I will use same valuation class but I want two different GL accounts to be hit.
Why is batch record important?
How can you disable a reservation in mrp?
What are some of the other erp applications available in the market?
What is sap? How is it used in industries?
Explain the basic 'organizational structure' in mm?
What is a 'batch' in the context of 'batch management'?
What is the source of error "not allowed" in case of custom movement type creation?
What is a batch?
How is the vendor created?
What are the terms planned delivery and gr processing time?
What is a blanket po? In which business scenario you will recommend to use blanket po?
Under which business scenario split valuation is used?