You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization’s operating system on 236 servers. You performed this project under contract. You are in the Closing process and know that product verification is for what purpose?
A. To verify the goals of the project and assure the product of the project is complete
B. To evaluate all the work of the project and compare results to project scope
C. To verify all the work was completed correctly and satisfactorily
D. To evaluate project goals and assure the product of the project meets the requirements
Answer Posted / Chandra Kant
C. To verify all the work was completed correctly and satisfactorily