Which of the following is true regarding the scope statement?
A. It describes how to make changes to project scope.
B. It describes project deliverables and serves as a baseline for future project decisions.
C. It assesses the stability of the project scope and is a baseline for future project decisions.
D. It assesses the reliability of the project scope and describes the frequency of changes and their impacts.

Answer Posted / Mandeep Kumar Srivastava

B. It describes project deliverables and serves as a baseline for future project decisions.