You are the project manager for Zippy Tees. Your company has decided to outsource the manufacturing of miniature bears to be attached to your trendy T-shirts. Which of the following is true?
A. A good product description is all that's required. The project manager will supply this to the vendor.
B. The contract can serve as the project charter. The product description will be included in the contract.
C. The project manager should write the project charter because the project manager will be managing the vendor portion of this project as well.
D. The vendor should write the project charter as they are responsible for manufacturing the bears.

Answer Posted / Dhirendra Kuamr

C. The project manager should write the project charter because the project manager will be managing the vendor portion of this project as well.

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

No New Questions to Answer in this Category !!    You can

Post New Questions

Answer Questions in Different Category