how can calculate material in 1:1.5:3 ratio in concrete

Answer Posted / madhusudhan

for 1 m³ concrete (M20=1:1.5:3)the material required is
(1+1.5+3)=5.5
1/5.5=0.1818*1440=261kg cement or 5.32 bags
1.5/5.5=0.272 m³ Fine aggregate
3/5.5=0.545 m³ Coarse Aggregate

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Can anyone tell me the sequence of the activities in a drawing room, kitchen & Toilet including civil work, finishing, electrical & plumbing fittings

1653


Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.

2372


how water proof chemicals act in concrete to avoid leek?

1776


What is the difference between linear dimension and aligned dimension?

640


1. For 10sq.m area(47 kg bitumen contain) of 45 mm thick bitumen mix layer..how much bitumen is required for 1600 sq.m and how much aggregate need for that ?? 2. And much tonnage of bitumen mix required for 10 sq.m area of 45 mm thick. Please give answer...

1637






why do we not deduct volume of steel to find actual volume of concrete in practical???

1329


WHAT WII BE THE WATER ABSORPTION POWER OF WOOD ?

1785


the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm

1890


57. Calculate the volume of a truck loaded with stone chips whose data are as follows– 5 Top Length - 13-9, 13-10, 13-09 Bottom Length - 13-11, 13-10.5, 13-10 Top width - 8-7.5, 8-8, 8-7 Bottom width - 8-7, 8-8, 8-7.5 Depth - 2-0, 1-11.5, 1-10, 1-11, 1 -10.5, 1-11.75, 1-11

9053


what is the effect of duration of earth quake on framed structures ?

1813


trapozidal

2015


what is the use of water bar in water tank and is this an extra item in estimate?

2124


How to make a c++ program that converts any base to base 10?

1625


calculate the quantity of cement ,sand,bars and aggregate used for 28*4 ft with 4 inch (125mm) thick

1368


What is the sugested procedure of water purification for public supply?

1723