Your company manufactures small kitchen appliances. They are introducing a new product line of appliances in designer colors with distinctive features for kitchens in small spaces. These new products will be offered indefinitely starting with the spring catalog release. Which of the following is true?
A. This is a project because this new product line has never been manufactured and sold by this company before.
B. This is an ongoing operation because the company is in the business of manufacturing kitchen appliances. Introducing designer colors and features is simply a new twist on an existing process.
C. This is an ongoing operation because the new product line will be sold indefinitely. It's not temporary.
D. This is not a project or an ongoing operation. This is a new product introduction not affecting ongoing operations.

Answer Posted / vhin84

C

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are the framework activities and umbrella activities?

558


Write about organising and staffing in management.

557


The VP of customer service has expressed concern over a project you're involved in. His specific concern is that if the project is implemented as planned, he’ll have to purchase additional equipment to staff his customer service center. The cost is substantial and was not taken into consideration in the project budget. The project sponsor insists that the project must go forward as originally planned or the customer will suffer. Which of the following is true? A. The VP of customer service is correct. Since the cost was not taken into account at the beginning of the project, the project should not go forward as planned. Project initiation should he revisited to examine the project plan and determine how changes can be made to accommodate customer service. B. The conflict should be resolved in favor of the customer. C. The conflict should be resolved in favor of the project sponsor. D. The conflict should be resolved in favor of the VP of customer service.

614


Which of the following contracts should you use for projects that have a degree of uncertainty and require a large investment early in the project life cycle? A. Fixed price B. Cost reimbursable C. Lump sum D. Unit price

947


How will prioritize tasks in your projects?

485






Information-gathering techniques used in the Risk Identification process include all of the following except: A. Brainstorming B. Delphi technique C. Interviewing D. Kaizen technique

688


Comparative methods, scoring methods, and economic and cash flow analysis are all part of which of the following? A. Benefit measurement methods, which are a tool and technique in Initiation B. Constrained optimization methods, which are a tool and technique C. Benefit measurement methods, which are an input to Initiation D. Decision models, which are an output of Initiation

830


You are a project manager for Penguin Software. Your company creates custom software programs for hospitals and large dental offices. You have just completed a project and are gathering the documentation of the product of the project. This might include all of the following except: A. Technical specifications B. Electronic files C. Programming plans D. Performance measurements

558


You are a project manager for Fountain of Youth Spring Water bottlers. You are installing a new accounting system and have identified several problems and their causes. You decide to use which of the following to identify the variables that will have the greatest effect on project outcomes? A. Design of experiments B. Bench marking C. Benefit/cost analysis D. Flow charting

606


How to deal with underperforming team members?

600


All of the following are characteristics of the project Closing processes except: A. Probability for success is greatest here. B. The project manager's influence is greatest here. C. The stakeholders' influence is least here. D. Risk is greatest here.

788


What are the Quality Planning process outputs? A. Quality management plan, bench marking, checklists, evaluation criteria B. Quality management plan, bench marking, operational definitions C. Quality management plan, checklists, inputs to other processes D. Quality management plan, operational definitions, checklists, inputs to other processes

556


You are the project manager for a top-secret software project for an agency of the United States Government. Your mission, should you choose to accept it, is to complete the project using internal resources. The reason is because getting top secret clearances for contractors takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Your programmer’s are siphoned off this project to work on the executive director's hot new project. Which of the following addresses the purpose of Scope Verification in this case? A. It determines the correctness and completion of all the work B. It documents the level and degree of completion C. It determines if the project results comply with quality standards D. It documents the correctness of the work according to stakeholders' expectations

673


What is one of the problems with project management software? A. The project manager manages the software instead of the project B. Project duration calculations are sometimes approximate. C. You cannot override the project management software decisions regarding schedules. D. It’s expensive and difficult to use.

621


You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis. When you've completed this process, you'll produce all of the following outputs except: A. Overall risk ranking for the project B. List of prioritized risks C. Inputs to other processes D. List of risks for additional analysis and management

675