how much quantity a carpenter do shuttering per day
Answer Posted / shawaiz khan
3 to 4 m2 per day should be done by carpenter with one helper
| Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
indian standard split spoon sampler
what is zone a n zone b?why the spacing of ring in zone a less.n zone b high?
How u can calculate the Octagon ring distance from center of raft in 275 mtr chimney slipform errection? cantact no:0993455097
What is meant by a context menu in a cad software?
what is the theoritical percentage of concrete cubes testing per day?
what else we can add rather than admixture in concrete to reduce the cement quantity?
If we buy crush sand for 3200/ Brass and cement for Rs350 /Bag and flyash 1200 / tonne....and my production is 230 Bricks per bag than how much cost is required for 1 flyash brick?
660 square fit two story house make totally how much cement, sant, brick,aggregate, steel totally how much need
WAP to print 1) 1 1 1 1 1 1 1 1 1 1 2) 1 2 3 4 5 6 7 8 9 10
how we calculate the vol.of wet concrete..?
Which are the Steel tests ?
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?
Detection of a beam & a girder areββββ
what is the design procedure for building
if i used salt as a add mixture in concrete, then what will happen and what are the naturally available add mixtures.