how to decide cement quantity in 1 m3 concrete
Answer Posted / mehar
For example take m15 grade of concrete.. It's ratio 1:2:4
1+2+4 =7
So cement having 1 m3 wet volume.
But dry vol= wet volume x1. 54 m3(45-55 % of dry volume)
Wt of cement =(1x1.54x1440) /7 = 312kg
Convert to bags = 312/50 = 6.25 bags
So for 1m3 of concrete work of m15 grade comcrete nearly 6.5 bags of cement if required..
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
plz.show development and anchorage length in simple diagram.
can you please tell me what the current rate of construction material and different construction labourers charge in bangalore ???
Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting
While calculating the weight of the steel per running meter, the formula used is [(dxd)/162]. Why 162 is used in denominator & how it is derived?
I need to constructive work in amaraj batteries
What is the strength of 1:6:12 mix?
pls mail some more tecnical qustions at msaranya2610@gmail.com
i want to ecil (Electronics Corporation of India Limited Hyderabad) previous civil engineering question papers immediately please.............
Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.
Technical Question of Civil Engineering
what is the 0 value in quantity surveying
400 ku d/c clearess ketan hota hai?
Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.
material used for mendrel use to bend epoxy coated rebar
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?