1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"
Answer Posted / sidhaant gupta
cement = 1*0.3/7*1440 = 61.71 kg or 1.234 Bags
sand = 9.08 Cft
Bricks = 451 Nos
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What is the sugested procedure of water purification for public supply?
how to identify np3 pipe and np4 pipe
What is the difference between pvc,cpvc and upvc and where it is used as per their properties?????
what is Short bored pile foundation.
difference between trapezoidal and pedestal footing and how the load acts on that
What is a hatch patterns?
Is there the dry coefficient of cement is constant?
What is unit weight of normal concrete?
How to arrive the co- efficient of all civil activities? For ex:- painting-enamel in wooden doors. co efficient is 1.8. How this is calculated
Which type of plywood & sizes using in construction projects ?
how much quantity of cement,sand and water required for 1 sq feet flooring work .
How much percentage of brick bats allowed in CD-75 bricks
How to find coloumn vertical cut length floor to floor & lap + bend or anything plz clearfiy
i have applied 40mm spacer in the concrete for tie beam. is it correct? kindly give me if there any code available
how to decide the mortar ratio 1:4,1:6 in masonry? same in plaster 1:3 and 1:4? which code or any document reference taken to define proportion?