how must steel will use for 1 cubic meter.formula of steel
for beam,column,lantern.
Answer Posted / mahi
mahi
Required steel in concrete is Depend on Types on concreting different structure
For Example,
R.c.c Slab = 0.5 to 1 % steel Required in volume of concrete
R.c.c Beam = 1.8 to 2% % steel Required in volume of concrete
R.c.c column = 2.5 % % steel Required in volume of concrete
R.c.c Road = 0.6 % % steel Required in volume of concrete
(1) Here take Column 1 m3 concrete volume calculation is
(2.5 x 1/100) x 7850 =196.25 kg steel Required
Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
How to calculate quantity of cement , sand and granite from concrete mix ratio and volume of work
Which is stronger solid steel rod or hollow steel pipe?
How to calculate brick work quantity?? Block work quantity??
where can i get the previous question papers for rrb section enginerr (civil)
What is GSB gradation
who to find building iron rod strenth
Explain what is zoning permit?
Basic civil interview questionsÂ
what is polity
I want some common questions which have been asked in interviews of NTPC Limited,Satluj Jal Vidyut Nigam Ltd.,and Bharat Heavy Electricals Ltd.
CAN WORK WELL UNDER DEAD LINES OR PRESSURE?
How do you measure water flowing through 300mm diameter pipes?
What is the cost of formwork for columns/beams/rcc walls also what is the cost of shuttering for roof slab at height of 25 feet
What is the minimum size of the particles of silt soil?
In cement concrete how to check a quality of material also proportion of material at site ?