Answer Posted / agin nadar
MD04 - Dynamic in nature ie. It shows current situation for stock i.e. it is updated continously.
MD05- Static in nature, only shows result of last MRP run, but in between if any procurement is raised is not updated in it.In short it is updated on MRP runs.