how to calculate rate analysis of M25 grade concrete
Answer Posted / br rijal
Solution/ BR Rijal
Volume of dry concrete = 1.54 to 1.57 times volume of wet concrete
so,
calculation for 1 cu.m of concrete works:-
summation of ratio of concrete M25(1:1:2) = (1+1+2) = 4
Shrinkage Factor = 1.55 ( Assumed)
so,
Total volume of wet concrete required = 1.55 cu.m
Now,
Volume of cement required = (1/4)* 1.55 = 0.388 cu.m
= (0.388 / 1440) = 558 kg
cement required = (558 / 50) = 11.16 bags
volume of sand required = (1/4) * 1.55 = 0.388 cu.m
volume of Aggregate required = (2/4) * 1.55 = 0.775 cu.m
Therefore, For 1 cu.m of M25(1:1:2) concrete works;
cement required = 11.16 bags
sand required = 0.388 cu.m
Aggregate required = 0.775 cu.m
| Is This Answer Correct ? | 3 Yes | 2 No |
Post New Answer View All Answers
01. a. Diagram of a slump cone…………… 1 b. Size of Slump Cone…………… 1 c. Volume of a slump cone by av. Dia method…………… 1 d. Volume of a slump cone by av. area method…………… 1 e. Volume of a slump cone by frustrum method …………… 1 f. Angles of slump cone …………… 1 g. Slump measured by slump cone due to…………… 1 h. Slump does not measured by cylinder / cube due to …………… 1 i) ii) i. Slump cone is to be filled in……………………..Layers.
How to calculate the crank rod in slab
Can rice husk ash be used instead of coal fly ash for manufacture of clc/ foam concrete
What are the methods of measurement? Describe it shortly
What is the standard volume of pharma in cub ft
what are the values of compressieve strenght?
List out some of the common problems that architect have to tackle it?
what are the layers of the national and heir aprox thickness??
List out some of the software used in the construction sector to estimate cost and monitoring expenses?
Why are steel plates inserted inside bearings in elastomeric bearing?
Describe Briefly The Various Methods Of Concrete Curing?
What is meant by engineering drawing?
how many spacers we need for 1 ton reinforcement? aprox.
What is a tensile strength? What is the tensile strength of wood?
do you think we shall remove un wanted soil for foundation excavation even if the thickness of the soil strata is more than 8m ?