why we do multiply 1.54 for dry volume of concrete?
Answer Posted / ramya
If wet volume is converted into dry volume then dry volume is raised 54% of wet volume
Hence, dry volume : Wet volume➕ 54%wet
. volume
dry volume : ( 1➕ 0.54 ) wet volume
. dry volume : 1.54 * wet volume
| Is This Answer Correct ? | 9 Yes | 1 No |
Post New Answer View All Answers
what is called the inverd level of mabhole chamber?
How to find CN by using arcgis 9.3?
though u r a civil engineer, y r u interested in tcs???
how to caliculate required amount of cement and sand required for 1cu.m.
What are the techniques to measure road difference?
What is difference between combin footing & rapt footing
1.Fe500 and Fe550 having more yield strength than Fe415.But why are we prefering Fe415.? 2. d^2/162 formula for knowing the steel wt/m apply all these three? Thanks.
why the profile of shell of natural draught cooling tower is hyperabolic.
In the present situation of ban on mining sand from rivers,can we go for formation of earth dam filters viz;Horizantal sand blanket,inclined chimney and filters under rivetment with crushed rock sand of 6mm down size.If so what are the specifications and is there any codal provision for its authentication?
what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?
WHAT IS YOUR CURRENT SALARY
Please tell me vasthu room sizes. Thanks.
Slump Values for works?
What is the difference between Fe 500, Fe 500 D and Fe 515.
i just want to know how much require sand and cement for 1 sq.mt including wastage. Please guide me as soon as possible.