Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

What is the thumb rule for calculating the number of chairs in slab?

Answer Posted / 9040471784

1. Chairs are provided for maintain the proper gap between the 1st layer & 2nd layer.
2. In IS Code it is not mentioned the chair spacing.
3. As per my experience it should be provided 1 chair in 1 sqm.
4. If the slab is 6 sqm then there will we use 6 nos of chairs

Is This Answer Correct ?    10 Yes 5 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

natucher of concrete &type of concrete?

2410


List out some of the software program that can be useful for architect?

1104


What is the difference between Grade I, II and III of GSB?

2639


What are advancements in civil engineering?

1055


Define absolute co-ordinates?

1289


How to calculate cement, water, fly ash amount for 1 cum if the w/c ratio is 0.4 and fly ash to cement ratio is 1:9

2059


Could you please give me an answer to the mixing proportion of concrete M1 grade (sterngth of 1 MPa)?

2624


what is the use of water bar in water tank and is this an extra item in estimate?

2571


Can we weld hot rolled steel ASTM A615 ? Please Give the detail answer please thanks alot

2243


How many kilo-newtons equals 1000 kilogram?

1145


in design case of structural member best suitrable percentage of steel limit is what

1509


For what purpose bedding is used under storm water drains?

1101


strength of bitumen concrete with 80-100 & 60-70 grade bitumen

2103


qty. of cement & sand required (100sq.mtr) for fixing of floor and wall tiles also fixing of marble stone on the floor

2243


What is the difference between EPC,DBOOT and BOOT.

24836