how to calculate the cable size for 500 kva transformer?
Answer Posted / ezhil
the full load amps of 500kva transformer is
kvax1000 / 1.732 x v
500x1000 / 1.732x415
500000/719 = 695A
Hence we can select 2R X 3C X 300SQMM
| Is This Answer Correct ? | 16 Yes | 3 No |
Post New Answer View All Answers
RESPECCTED SIR/MADAM- I AM PRERING FOR SECTION ENGINEER (ELECTRICAL) RRB CHANDIGARH PLEASE SEND ME SOME PREVIOUS YEAR QUESTION PAPER OR MODEL PAPER.MY EXAM IS ON (30- NOVEMBER 2008).I AM VERY THANKFUL TO YOU. FROM- HARENDRA SINGH YADAV
If 22 KV HT line, Current transformer is 25/5 then how to calculate multiplying factor.
7- What is the Dissipation Factor and the difference between it and Insulation Resistance Test? 8- What is the task (function) of DC and AC reactors in power plant? 9- What is the task (function) of (open delta with earthed) in some types in transformers? 10- What is the base of the selection of the vector group in transformers? 11- What is the zig-zag transformer and its function by drawing in large detail? 12- What is the polarity ? 13- Why we make short between phase(R) in high side and phase (r) in low side in vector group test? Where High Side ( R ,S and T ) and Low Side ( r ,s and t ). 14- What are the time on delay and time off delay? 15- What is the vector group? 15- What is the task (function) of different types of vector group such as Dyn11 , Dd0 , YNd1,……..,?
What is referred to the electron in the outer orbit?
DEAR SIR/MADAM,CLEARLY EXPLAIN ABOUT CRAWLING AND COGGING EFFECTS IN INDUCTION MOTOR.
what is your aim
what is the voltages using in movie theaters??? why ??why not other??
how much maximum load a 2 core (Single phase) 16mm aluminium wire can take ?
What is routh hurwitz stability criterion?
What are the functions of temperature scanner in power transformer?
What test must you do before powering up a circuit that you have been working on?
how can service sitting be setted for MCCB?Example for sittings IR (CURRENT RATING),IS(CURRENT STARTING)IO (current operating)?
An ISP is granted a block of addresses starting with 150.80.0.0/16. The ISP wants to distribute these blocks to 2600 customers as follows. a) 200 medium size businesses; each needs 16 addresses b) 400 small businesses; each needs 8 addresses c) 2000 households; each needs 4 addresses Design the subblocks and give the slash notation for each subblock. Find out how many addresses are still available after these allocations.
Can any one give an explanation about rating factors of cable? if we are laying the cable on the air with an temp 15 degree then rating factors will be 1.15 and if we are laying the cable on the air an temp 60 degree then rating factor will be 0.76 please describe it and what is the difference between rating factor and derating factor?
The 3 phase 400 hp 440 volt slip ring induction motor do not take one phase amps why ? The motor is running good condition