Answer Posted / pradip
variant material means the material is to be used for many times in diff bom. ex if a company manufacturing diff types of bicycle then the bom is also diff but if some material is same for all bom then we treat that material as a variant
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
what are the problems you faced in MRP?
What is the output of mps run ?
What are the different type of BOM usage?
Explain how the pp module is organized in sap?
After doing realization how we will check whether it is working or not?
What is the use of mrp list?
Explain PI sheet.
What is Schedule Margin key. How floats works in scheduling?
What do you mean by basic dates
what do you mean by planning time fence
Integration between PP and MM Module.
Can any body explain me why work scheduling view is required for semi finished and finished products?
What is planned consumption and unplanned consumption?
How costing is affected the pp?
How system calculate the actual cost?