calculation of cement bags in 1:2:4 concrete mix
Answer Posted / basharat ali
1.54/sum of ratio
1.54/7=.22cum cement
.22/.0347=6.340bags cement (Say 7)
.22×2=.44cum :-15.5368cft :-19.047bags
.22×4=.88cum:- 31.07cft:-38.09bags
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
In case if concrete box girder bridges how is the number of cells determined?
Curing time for 1)R.C.C slab 2)B.W 3)Plastering
Define What are the uses of alloys in daily life and how are alloys made?
Can any body help me out by telling hoe swelling pressure test of soil is carried out ? some body told me the procedure & formula (change in length /116.3*100%) but still i am confused ? pls help.
How did the romans get water up hills using aqua ducts?
For what purpose bedding is used under storm water drains?
one steel fixers how much ton steel fabrication he will do same how much tone he will binding?
if size is 235cmsx15cmx100cms so how many cement bags and how many sand bags are used for concrete mix
Which are the top apps for you civil engineering?
what is the anchorage length of reinforcement.
what is floating slab foundation?
Pls help me to arrive the rates for centering shuttering for highbay using H-frames?
what are the types of design? which type of method is used at what type of design & why?
any book or article on pumped concrete.
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.