I am working in a process industry, in that there are
several sections devided in the SCADA screens and
individual sections may START independently. But sometimes
i am facing problem i.e, if section 2 Stopped by the
operator immediately Section 1 or Section 3 or Section 4 is
getting stopped can you expain the reason behind this?
Answer Posted / jitendra chauhan
following problem may:
1. Is same interlock may used other sections?
2. have you checked stop command DO of all section, may that same DO?
3. may network getting stop, may PLC going to stop while given to stop command?
4. may that same stop command linked on SCADA?
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
i am preparing for BARC ,so plz mail me how to prepare for BARC. ALSO IF POSIBLE SOME RELATED QUESTIONS. MY MAIL ID IS khushi_4uall2003@yahoo.co.in
What is stripper & spilitter ? Diffrence in this.?
how pressure transmitter work, what is its principal to measure and how its generate signal. for pressure transmitterinstallation which precautions must be taken ??
what is commisioning procedure,2)what is is the main work in commisioning in the field tx to dcs, plz send me detail
Hi, Is there any smart plant instrumentation design training institute in Bangalore?
How is work 5/2 sov?
Difference between ultra sonic flow meter
Can anybody tell me which type of question are asked in the interview for the FORMULATION(Pharma) as a instrumentation engineer, & question in building managment system.
what is loop1 and loop2 in MTS LT?
How can we test a bently nevda 3500/42M accelerometer monitor card by simulating it with test equipment?. what king od of signal (milli volts or volts or or resistance ) we should feed in the terminals of the card?
What is instrumentation control?
why would you like to join our company
What is the use of control cable?
What is heating effect?
can any one explain in which term we are flow flow is it volumetric r is it mass? and y