• What types of scrap can be maintained in PP basic data and
how would they be considered during MRP repectively scheduling?
Answer Posted / mohamed ibrahim
types of scrap
1- assembly scrap
increasing the assembly % in prod.order consequently increasing its components
maintain it in MRP1
2-component scrap
one component loss of QTY during production that's require increasing its QTY.you maintain this in item details in BOM and in MRP4 view
3-operation scrap
during an operation, there was a loss of QTY that require the operation scrap. you maintain it in BOM item details with check NET ID that indicates the QTY loss and also in a routine that indicates the activity loss
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
How to attach a drawing for a material to bom ? Is it possible ?
What is end user training
What is collective order. Pre requisite of the collective order?
Consignment matl how will be use
What are the three 'mrp procedures'?
Differentiate ‘variant bom’ from ‘multiple bom’?
Is it possible to convert a 'multiple bom' into a 'variant bom'?
What are the MRP master data?
What is Inspection Points?
What happens to planned after it has been converted into production order ?
Explain the gaps and the steps involved in them.
Explain Planning file entry.
What is mrp controller means?
IM GOING TO GO FOR AN INTERVEIW SOON AND I WANT TO KNOW WHAT SAP PP INTERVEIW QUESTIONS ARE LIKE. I DONT HAVE A REALTIME EXPERIENCE THOUGH. ITS MY FIRST TIME
What is the data you give in S.O.P screen?