• What types of scrap can be maintained in PP basic data and
how would they be considered during MRP repectively scheduling?
Answer Posted / mohamed ibrahim
types of scrap
1- assembly scrap
increasing the assembly % in prod.order consequently increasing its components
maintain it in MRP1
2-component scrap
one component loss of QTY during production that's require increasing its QTY.you maintain this in item details in BOM and in MRP4 view
3-operation scrap
during an operation, there was a loss of QTY that require the operation scrap. you maintain it in BOM item details with check NET ID that indicates the QTY loss and also in a routine that indicates the activity loss
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
Explain transaction code KO88 or CO88.
What is prt (production resource tools) in sap pp?
How requirements( pir,sles order, customer requirement) are reduced after they are produced?
What is the uses of production scheduling profile and what the configure have you done current project
Can’t one material be assigned to more than one operation in a routine?
What is alternate item group?
Are there any reports in sap to list of material requirement from ltp ?
what is alternative item group
What is MRP Profile and MRP Group?
What is meant by payscale structure? How did you configure the payscale structure?
How the processing time is calculated in a wc when both labor, machine categories exist?
What is the difference between stock transport order and stock transfer order?
Explain the planning steps for 100 products?
What is MRP procedure
What is the recruitment cycle?