how many bricks required for below volume 1. depth filling 0.00 Qty 1.61 & Unit Cu.M
2. D-Filling 300 Qty 2.0 & Unit Cu.M 3. D.Filling 450 Qty 2.24 & Unit CU.M 4. D-Filling 600 Qty 2.44 & Unit Cu.M
Answer Posted / suman
750
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
How much 1 cum of M15, M20 & M25 concrete weigh?
While calculating the weight of the steel per running meter, the formula used is [(dxd)/162]. Why 162 is used in denominator & how it is derived?
how to identify the failure of building by expansive soils
Permissible wastage of cement as per IS code ? In which IS code I get it?
How to calculate woden area in sft and Cft
what is castigliano theaorem
States some of the commonly used commands in cad software’s?
How much the quantity of Dry material of Crush for 1:2:4 Concrete, using pan 3/8'' down....
what is the hanekom repairing material after concreting work
WAP to print 1) 1 1 1 1 1 1 1 1 1 1 2) 1 2 3 4 5 6 7 8 9 10
What is meant by Crystal Concrete?
Why Is Propping Required For Long Structures Once The Form Work Is Removed?
Explain major differences between routing maintenance and major maintenance.
manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.
how to do cementicious paint for rcc walls of cw pump house