how much cement is required for 3200 sq ft of roof
Answer Posted / lalit
consider a nominal mix
1:4:8
cement:sand:coarse aggregate(the above nominal mix is always per volume)
now let's consider depth of roof as 1 feet.
now 1 bag of cement=1.25 cubic feet.
so let's cement volume is x,
then sand=4x and coarse aggregate=8x
now,
x+4x+8x=3200*1 cubic feet
find x,now from this value find out the no. of cement bags by dividing x by 1.25(of each bag)
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
Floor to floor high of domestic building is 3m design a quarter turn staircase starting assume taken give a suitable diagram of it?
what is the service corridor?
What is the snap size in civil and how can we create it?
What is the use of extruded feature in solidsworks?
Dear Frds, How can i calculate the Steel for RCC Slab, Please provide one Example also, so that i can understand very well. Ex: Area: 1320.0 Sft.(44' X 30') Span: 15'(Default). Column Size: 9"X15"(6 No.s 12mm Rods) Please Provide Calculation Details. Thankyou. Satish
how much cement sand n bricks required in im3?and how much in plaster?
How to calculate material and labor required for 100 m2 plaster?
how much to get of BRC lapping in full yield and half yield ?
WHAT R THE GENERAL TECH QUESTIONS ASKED FOR THE INTERVIEW FOR AN AUTOMOBILE INDUSTRY,SPECIALLY DESIGN DEPT
what are the challenges of being a team leader and a supervisor?
what are the ffactors you considered choosing the course?
in one SQM plaster how much Cement and sand consumed in ratio 1:4
How much river sand contain the 6 & 10 wheeler truck? Or Maximum sand that any type of truck carry?
sir i want to know that in L & T construction can we do our 6 months training proggramme cum placement???????
when it is noted "JAMB SIM" what is the term "SIM" and what does it mean?