Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

where we use one way slab and two way slab?

Answer Posted / akram

L/B value is = more than 2 then these slab is Called as one way slab. in this slab the main Reinforcement will be providing in one direction.

L/B value is = Less than 2 then these slab is Called as two way slab. in this slab the main Reinforcement will be providing in both directions.

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the bowing depth after stressing of PSC Girder of various spans and various dia of strands?

2339


What is made from large rocks, which protects the base of cliffs?

1373


What is the strength of cement?

1327


how to decide the mortar ratio 1:4,1:6 in masonry? same in plaster 1:3 and 1:4? which code or any document reference taken to define proportion?

2195


A 16 pile group, consisting of diameter concrete piles, were cast in situ in a clayey soil whose unconfined compressive strength is 1100 psf. Each pile is 60 ft long and the pile spacing is 2.5 times the pile diameter.The water table is at the ground surface and saturated unit weight of the clay is 118 lb/cu.ft. using a factor of safety 3 and a reduction factor =0.45, compute the allowable capacity of the piles acting as individuals

2317


Form where IS456 is adopted in 1978?

2045


What is Grid floor and mention its advantages ?

3304


Explain what is the difference between built area and super built up area?

1248


what is the criteria for the finalisation of pavement thickness in road project?

2187


Define current ucs?

1499


How much material is required for constructing a 2 Lane 2Km rigid pavement road

2257


What does civil status mean?

1251


Curing time for 1)R.C.C slab 2)B.W 3)Plastering

2148


Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.

3526


what is Quantity of stone and sand required for one cubic meter of stone work (UCR)

2156