what is quantity of sand required to plaster wall about
1000 sq ft
Answer Posted / v ramesh
area in m^2 = (1000/10.76)=92.95sqm..
volume=92.95X(12/1000) = 1.12M^3
add 30 t0 35% of bulking of sand= 0.336M^3
add 20% for wastage of sand = 0.224M^3
total = 1.68M^3
=(1.68/(1+4)) = 0.336m^3
=cement = 0.336*30=11 bags
= sand = 0.036*4 = 1.344M^3 of sand
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
How to find the cuplock pipe qty in staging for Minor bridge?
psc girder detail
In few lines, please be elaborative on extras and talents that make you a potential candidate for the post:
What is the wall thickness of NP-3&NP-4 hume pipe as per I.S code
How will you reduce the concrete flow after mixing the concrete
how to identify np3 pipe and np4 pipe
how much used soil in 1 brick of standard size?
how much of quantity of material required for execution of one cubic meter of random rubble masonry in 1:3 cement mortar
what is the weight of 10mm,20mm,40mm aggregate
what will be the total emoluments for deputy surveyor in APPSC in the payband of ( 9460-27600). please give me the detailed information step wise?
How to calculate construction cost of residential building in mumbai
How do you compute moisture correction using the parameters gathered from Nuclear Density Gauge Apparatus and the moisture contents results from the lab.?
There are two buildings one taller and one shorter whose time period will be grater and similarly the frequency ?
How do you prepare Material Recovery Statement for deduction from contractors bills?
why we are useing plastic under the lean concrete?and whts the advantage?