Answer Posted / n.prabakar
DC supply only for breaker control because ,if plant came to blockout we cant resume even EB suppy without breaker close.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
Why and when NGR panel required. Is it necessary to design a NGR panel for a 6.6kV Alternator paralleling with Grid????
How should i design a 1ph & 3 ph transformer. Kindly let meknow all steps and formulaes related to design from scratch.
Is a contactor (or master relay) required between incoming lines and a VFD? The question goes to safety. If a contactor were used before the VFD and an e-stop engaged then the motor will coast to a stop (i.e. VFD loses power) instead of stopping much faster if the VFD braking fucntion were used. It would make more sense to keep power on the VFD.
What is current & voltage ? Voltage perform at any load without current or not?
is it possible to say motor horsepower number without seeing name plate(when name plate damaged)
hi....I am from india..i have completed my engineering in electrical and electronics field with 58.4% and my IELTS score is 5.5 bands....Recently i received my I-20 in computer and information science from Troy university in Alabama.On 18th i have a visa interview can u please tell me what type of questions i have to answer ??????
We need to current density & short circuit calculation at 65kA for aluminium & copper busbar.
How do we calculate the resistance per metre of single core aluminium stranded cable 19*3.25mm sheathed in pvc,at 15 deg C temperature?
PLEASE SEND ME NTPC RELATED INFORMATION LIKE WHICH TOPICS HAV MORE SCOPE,BOOKS TO READ,CUT OFF...PLEASE.mail at thiru.1203@gmail.com
Show Details FROM:Muhammed Ikram TO:qa@allinterview.com Message flagged Saturday, June 4, 2011 10:07 PMMessage bodyHello all, i want to ask a question to all of you that what is VMM (voltage monitoring module )? how it work,s? i heard somewhere that it compare 1 phase voltage to other phase voltage. but there is also some setting on it. how to set it,s setting. please tell me briefly. Thank,s and Regard,s. Muhammed Ikram.
Has someone here done a sizing for a generator (3 phase), its for a pumping station. If you have an example for standby/duty and both running (I) star delta (ii) Soft Starter.
I want to merge a cable..in between two metering Cubicals which contains CT's and PT's and Energy meter..before taking merger..what are the common things required?
can I improve the furnace power factor (10 mva transformer) by adding a capacitor bank before the transformer.Does system power factor vary a lot with the furnace PF?
how to copy from plc ge fanuc versamax series,all input and output, adress, and printout.
why Current is lead 90 degree and voltage is lag 90 degree in a capacitor.? why Current is lag 90 degree and voltage is lead 90 degree in an inductor.?