Difference between Milestone & Periodic Billing Plan? How
it is configured & where it is used? Give examples.
Answer Posted / goswami
Milestone billing means distributing the total amount to be billed over multiple billing
dates in the billing plan.
As each milestone is successfully reached, the customer is billed either a percentage of
the entire project cost or simply a pre-defined amount.
Periodic billing is used when you want to bill the customer at different points of time based on the periodicity or progress of the work
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
can some body give me some idea on integrations of sd and sap crm service
I created a new info structure and activated update rules for it. What is the best way to transport them into a productive system?
We want to explode bill of material automatically at time of order entry and explode an equipment bom in the sales order. What are the setting required?
What is the purpose of text item in item category?, How and why is it being used
How do you define document numnber ranges
A 'plant' is assigned to which of the entities in the sd organization?
Tell me a customization which you have done & worked for your client which is not in standard SAP settings? Explain the requirement along with detailed procedure & process,t- codes if any from your real time data in your project? This question is most frequently asked in many interviews.Please reply asap... Urgent!!!! Waiting for your response eagerly... Thanks in advance
What sap systems have integration capabilities with sap transportation management? : transportation management
Hi Team, this question is related to 3rd party. customer is given order for 20 materials and vendor delivered to customer only 10 material . As per my knowledge vendor invoice will be for 10 material and customer invoice will be for 10 material but my question is how billing quantity will change in sales order against which we have need to create customer invoice for 10 material only. what configuration we need to do for update sales order quantity for order related billing for customer. how vendor will deliver rest 10 material to close this order? could you please share your input with screen shot. Thanks in Advance.
What is sap posting period?
What is the difference between connected & unconnected lookup?
In back order process system follows backward scheduling or forward scheduling? please give ur valuable answers
What is division?
dear sd guru's..i am srikanth fico training fico..in sd-fi..i getting error's in outbound delivery ..vl248&vl461..i could not go for billing& icoming payment..i saw to solve those error message's from goolgle.but i could'nt solve...please give me solution in clearly...please sir's..!
I am in the va02 transaction for a sales order and want to reject the line items and cancel the entire sales order. What is the menu path needed to achieve this goal?