Difference between Milestone & Periodic Billing Plan? How
it is configured & where it is used? Give examples.
Answer Posted / goswami
Milestone billing means distributing the total amount to be billed over multiple billing
dates in the billing plan.
As each milestone is successfully reached, the customer is billed either a percentage of
the entire project cost or simply a pre-defined amount.
Periodic billing is used when you want to bill the customer at different points of time based on the periodicity or progress of the work
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
how to configure Supply chain management
List the basic elements of a customer master record?
List a menu path to access stock requirements lists?
how to define and assign value for mini oder value (amiw) condition type and which field cateloge we suppose to choice in v/03?how amiw and amiz work together?
What about your experience with EDI idoc, can you elaborate a bit of what’s your experience working with EDI and IDoc?
i have one sold to party that sold to party have 1000 ship to party but if create order system should take always 80 number ship to party how can you do this?
Hi, Can anyone proivde the soluiton for the below senirio, thanks in advance. We are providing test services to various sites of a corporate. Now, we want to bill as a single bill point i.e. Corporate office. Single bill for each site will be generated. E.g. Panac Labs, New Delhi Head Office Panac Labs, Mumbai Lab at Mumbai Panac Labs, Kolkata Lab at Kolkata Panac Labs, Indore Lab at Indore In above case, we are cattering services to all four locations. However, New Delhi is the Head office and Lab too. Hence we will issue four bills addressed to Panac Labs, New Delhi. Outstanding and debtors will be maintained on A/c of Panac Labs, Head office. We also want to maintain sub- ledger base on sites
Can you assign two different sales organization to the same company code?
Change of sales document a sales document type of a sales order can be changed after getting saved. How do you do this?
Can I view the invoice due date (jan 16, 2006) in the invoice?
In back order process system follows backward scheduling or forward scheduling? please give ur valuable answers
I am an MBA[Marketing]; having more than 6 years of pharma sales experience and more than 2 years of sap-sd functional relevant experience . I am looking for a suitable change but in KOLKATA .Will any one inform me where to apply according to the vacancy in the respective company mentioning the HR dept.'s e-mail address ? I need an immediate change . arupkr73@yahoo.co.in
How do I change this?
Where do you define the terms of payment for a customer?
What are the user exits?