How to calculate the cement, sand quantity for plastering?
(10'x10')10mm thick ratio 1:5. wht"s the formula?
Answer Posted / vijay govardhane
Total area plaster: 3.05*3.05=9.3
(Convert area into sq.f):9.3*10.75=99.97
100/99.97=.9997(1 bag)..cement
..sand=99.97/100=.997
=.9997/17=0.058...brass
(17 is a standerd value of sand In single coat =17 cu.m)
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
How much is the cover for slab?
sir, please send me the web address of chennai railway to know the online examresults of junior engineer[civil].
B.M DIAGRAMS & S.F DIAGRAMS OF CONTINOUS BEAMS
I need Bhel engineertrainy test papers in civil engineering please send to email id - hisandy66@gmail.com
Why is the statue of liberty made of copper?
What is the l/d ratio of cantilever beam?
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
What the advantages and disadvantage of using 90mm and 100mm bricks for a wall of a house? Thanks for any input.
What is horizon or horizontal mining?
How will be cutting in timber plate size 600*400 column size
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
Whats the meanig of ,'K' VALUE in the case of soil.....
What is thumb rule for deep trench excavation
What is the tensile strength of wood?
what is right & short method of measurement of slab&beam