how much quantity a carpenter do shuttering per day
Answer Posted / shaikh shahrukh
4.45 sqm per day.
| Is This Answer Correct ? | 13 Yes | 7 No |
Post New Answer View All Answers
How will you Engage Labours on Site?
How to find permissible diagonal tensile stress in reinforced brick work
What is the outturn of Ceiling plastering
Why should you consider yourself fit to be hired by jindal steel.
Explain how you can turn off the display for dimension in CAD?
Explain the different types of building contracts?
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.
I need to do a Compressive Strength Test for a specimen made of Rubber. Before doing the Test on the Machine, I need to have an idea of the Minimum and Maximum Compressive Strength or Yield Strength of the specimen. How can I calculate that?
when reinforcement binding completed if there is more cover than the required what is the solution to reduce the cover?
What difference comes in constructing of house and a housing complex like society
Labor requirement for each item needed? Lean Concrete 103.550m3 Concrete for Foundation and Structure 1753.000m3 Expansion joint 288.000m Contraction joint 127.000m Dowel bar 450.000m
What is the maximum crushing load in Kg & crushing strength in N/mm2 for M25 & M 15 Grade concrete
For the calculation of bearing pressure below the footing, to know whether it is below the safe bearing pressure of the soil, the unit of RCC below ground level to be taken is 25 KN/m3 or (25-15)KN/m3, where 25 is the unit weight of RCC and 15 is the unit weight of soil and whether the weight of backfilling to be taken?
how to calculate the crushing strength of cement concrete paver blocks 100x100x60 mm thich.
What is meaning of tlc