If the design CBR of subgrade is 10% but the material available on site is 30%.will you compact less(like 90%) where you get desirable CBR(10%).
Answer Posted / rk
For increase the cbr must be added bending material like sand and granular particals for making proper cbr.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
in the earthquqke the profile of water on dam is parabolic or not
what is a well
Find out Cutting Length of Steel for Right angle Triangle? Where Opposite Side 4m, Adjacent side 6m. (Assume cover 40mm)
how much of the strength comes from post-production curing
I have to conduct load test on greting cover, pressure gauge is in kg cm2, how to caluculate load on this greting cover.
i need the syllabus for the direcr recruitement of executive engineers in andhrapradesh
types of survey and levelling instrument ?
Explain moment of inertia?
Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?
Define graphics window?
For the symmetrical continuous beam shown in figure, Prestressed with a force P = 1500 KN along parabolic curve as shown, compute the extreme fiber stresses over the central support for the uniformly distributed load of 24 kn/m. Use load balancing method.
how to calculate weight of 1.8 cum of aggregate
How many square meter can a worker/labor demolish a structure per day?
please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)