adspace


How to replace dia of bar in beam like 25mm 3no.S at bottom
But due to some reason on site 25mm bar is not available
Then is it ok to provide 20mm 4no.S? Give description or
Formula to calculate area of steel and replacement?

Answer Posted / krishna

Dia of bar pi/4*d2* no of bars.

If u replace the bars So pi/4*d2



:dia of bar/ replace of bar gives the total bars of available

Is This Answer Correct ?    4 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience

2556


can i get civil engineering test papers.......?????

2548


Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting

1895


Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.

2241


please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.

2397


how can we calculate steel value, depending on load

2441


hi, i am appearing in HPCL(CIVIL ENGG.)exam. plz send me placement paper of this exam if u are having

2599


Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.

2492


material used for mendrel use to bend epoxy coated rebar

2245


HOw much % of premium on DSR-2013 currently

2046


i want to ecil (Electronics Corporation of India Limited Hyderabad) previous civil engineering question papers immediately please.............

3223


Technical Question of Civil Engineering

2358


In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

2232


cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com

2264


pls mail some more tecnical qustions at msaranya2610@gmail.com

2178