Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

50m3 concrete volume how much cement sand aggregate details radio m20grade

Answer Posted / krishanu

I think 50m3 concrete volume is the dry volume of concrete. So wet volume of the concrete is 1.54x50=77m3
for M20 concrete the aggregate ratio is 1:1.5:3
1. So, cement required= (1x77/5.5)=14m3=14x1440=20160kg=403.2 approx 404 bags
2. sand required = (1.5x77/5.5)= 21 m3
3. stone chips required = (3x77/5.5)= 42 m3

Is This Answer Correct ?    3 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How many kilo-newtons equals 1000 kilogram?

1153


How do you compute the volume of airflow?

1113


howto calculate the quantities of material used in fly ash brick after finding the volume??

1694


How to make tiles floor step by step procedure?

1975


How many square meter can a worker/labor demolish a structure per day?

2107


what is the cost differene of a same structure when it is constructed with brick masonary, and when it is constructed with concrete as a frame structure.????????

1947


Aptitude, reasoning, quants, verbal and technical question

1580


how to prepare site mix design

1959


If specific gravity of cement is less than 3.15 what is the cause?

2316


What is different between DI Pipe and CI pipe?

2155


How do you change a dimension value in solidsworks?

1241


What is progress payment?

1320


What is the difference between the concrete mix design carried out by IS10262 and by ACI method ?

2724


Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?

2140


What is the value of live load that should be incorporated in design of locker room and cash vault room while designing a building for commercial bank?

2732