How to calculate cement required for m20,m5 grade
Answer Posted / mujtaba hussain
For M20 concrete, The ratio of the mix is 1:1.5:3 (Nominal mix)
The total parts is 1+1.5+3 =5.5
Part of the cement is = 1/5.5
The total volume raw material for 1m3 of mixed concrete practically =1.52m3
Unit weight of cement =1440kg
Weight of cement per bag = 50kg
Now the calculation is =1/5.5X1.52X1440
= 397.98kg
In terms bags per m3 of conctrete is 397.98/50 = 7.96bags
| Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
sir i want to know that in L & T construction can we do our 6 months training proggramme cum placement???????
how to calculate quantity of bricks in circular manhole with examples.
For elevated service Reservoirs what will be the output of each skilled carpenter and bar bender.
1.Fe500 and Fe550 having more yield strength than Fe415.But why are we prefering Fe415.? 2. d^2/162 formula for knowing the steel wt/m apply all these three? Thanks.
In foundation design, while we do the base pressure check, we normally check if the attained pressure value is less than the GROSS BEARING CAPACITY of the soil which is the sum of net bearing capacity of soil and the overburden pressure. Actually, the overburden pressure acts against the net bearing capacity of the soil and I feel that we are actually increasing the bearing capacity value and doing the check. I feel that this is NOT right. Please clarify on this.
What is Critical path in Ms-Project ?
HOW MANY BAGS OF CEMEMT USED IN PER M2 OF PARTITION WALL
why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?
Explain what are the problems one might face while having a Cantilever balcony?
how to remove the quantity of metal 1 and metal 2 in concrete
What is the sugested procedure of water purification for public supply?
57. Calculate the volume of a truck loaded with stone chips whose data are as follows– 5 Top Length - 13-9, 13-10, 13-09 Bottom Length - 13-11, 13-10.5, 13-10 Top width - 8-7.5, 8-8, 8-7 Bottom width - 8-7, 8-8, 8-7.5 Depth - 2-0, 1-11.5, 1-10, 1-11, 1 -10.5, 1-11.75, 1-11
What is a kip?
which red: used in roof teping, then use only cement
What is the meaning of Brick- M 35 grade? Is it a common brick or it's a concrete brick?