How to calculate cement required for m20,m5 grade
Answer Posted / mujtaba hussain
For M20 concrete, The ratio of the mix is 1:1.5:3 (Nominal mix)
The total parts is 1+1.5+3 =5.5
Part of the cement is = 1/5.5
The total volume raw material for 1m3 of mixed concrete practically =1.57m3
Unit weight of cement =1450kg
Weight of cement per bag = 50kg
Now the calculation is =1/5.5X1.57X1450
= 413.859kg
In terms bags per m3 of conctrete is 414/50 = 8.28bags
Is This Answer Correct ? | 3 Yes | 1 No |
Post New Answer View All Answers
In cement making,what is meaning of blend,fineness,density.
What is aggregate?
what might be the problem faced in the near future if the M-sand is used in the place of river sand during wall plastering? (As per IS)
hii.plz send me hpcl placement papers for officers trainees for graduate engg plz my email id is ajm_knit@yahoo.com
Why should appointment store person for project ? what is the benefits for company ?
cement mortor 1:5 for 30 m2 12 mm tk plastering so how to calcualte its rate
What is min thickness,min grade of conc & age of PQC ?
how will calculate 4"thick solid block quantities 1m3 sand cement ratio and breack up detail
How to calculate or what is the process of calculation for making 1Metre squre area by AAC Blok which quantity of Cement, Sand & Chips are to be required?
What in your opinion makes you the most suitably qualified candidate for this post of civil engineering technician?
how many material required for brickbat water proofing of toilets.
importance of the soundness test to determine the quality of cement use for any construction
04. a. Slenderness ratio…………… 1 b. If the height of a stage is 15-0 & dia. of the prop is 5, the slenderness ratio is….… 1 c. If the height of a stage is 10-0 & dia of prop is 3, the number of bracing will be…… 1
Why the finite element method is lower bound solution?
what is the difference b/w full length and cutting length?