Answer Posted / r satya nagendra babu
stage - 01 fixing of boundries,
STAGE - 02 Layouting,
Stage - 03 Marking the footing for excavation,
Stage - 04 sub structure,( footing =s and columns uo to plinth beam )
Stage - 05 Super stucture ( Plinth beam to Slab ie,,,which is above the plinth beam )
Stage - 06 Finishings,( Brick work Plasting Painting And All other activites)
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What is the ratio of grades m5, m7.5, m10, m15, m20, m25, m30, m35, m40?
rimmer in pile foundation
How do we test on design and style in a software?
3. What are the disadvantages of your present job, things you do not like about it?
does a b.tech civil engineer fresher supposed to know how to design rcc structure?
In the design of bridge arguments what considerations should be made to select the orientation of the wing walls?
How we can calculate the cement, sand,bricks , water , quintity in 1:6 Ratio 1 cubic metre b/w and 1:4 Ratio in 1 Squre metre b/w????
What is the difference in painting using Roller and Brush? What is the paint consumption difference? As per IS one coat of painting is painting from left to right and top to bottom whether this can be done using roller ( Roller Stick height and feasibility) ?
What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil
How did street originate in the plumbing term street ell?
Suppose you planning to paint newly fabricated workshop building made of structural steel of 10 tons total mass. How many litters paint primer for 1 coat and 2 coat of top coat?
How does siphoning work?
how the calculation occurs if i want to mix 1cum of M50 concrete. please calculate every ingredients with detail calculation.
What do you mean by tolerance factor of concrete ?
How much material will consume for following specification water tank (9*7.5*6 feet)?