how can change 12mmdia@150c/c bar spacing to 16mmdia
Answer Posted / kunal chandra singh
We can calculate the weight of 12 mm rebar in 1 sq m area with 150 mm spacing after that we can calculate by compairing 16 mm dia with calculated weight per sq m area to calculate unknown spacing .
| Is This Answer Correct ? | 7 Yes | 2 No |
Post New Answer View All Answers
How to find coloumn vertical cut length floor to floor & lap + bend or anything plz clearfiy
Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––
For what building Built-on balconies are preferable? What are the advantages?
1.what is the mix proportion for cement soil compressed earth blocks? 2.how to calculate the mix proportion for cement stablised earth soil blocks?
how to find quantity of concrete in PCC M15
What is the density of 1:1.5 (Cement:sand) ratio in plaster? And Conversion in 12.5 mm thickness per square meter? Howmany Kg of Cement square meter in ratio of 1:1.5?
how calucate cement sand ratio for plstering
i need gate exam civil engineering question papers with answers
WAP to print 1) 1 1 1 1 1 1 1 1 1 1 2) 1 2 3 4 5 6 7 8 9 10
what is E
What are the Types Of DPC and its Thickness used?
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
How many mortar required for Brickwork of 1 Cu.m works??
I want to change job.If You have any vacancy please contact me in this mail id-parthamitra086@gmail.com.Myself partha mitra.Diploma in civil engineer with 4+ yrs. exp.Now in kolkata.If you confirm me then I will send my detail resume to you.Also send your mail id to me.My mail id is-parthamitra086@gmail.com.I will be very much thankful to you.
Is there the dry coefficient of cement is constant?